The construction of “Renessans Palace”

tkn The construction residential complex of a premium class - "Renessans Palace" is underway.

In block “A” of the first building, the construction is on the third floor, on block «В» and «С» on 6-th floor, on block “E” – on the first floor.

In blocks “A” and “B” of the second building reinforced concrete works is on the top floors. In blocks “C”, “D” and “E” reinforced concrete works are completed, the wall of top floors is laid by concrete wall blocks.

In blocks “A” and “B” of the third building the reinforced concrete works are on the 16-th floor. In blocks “C”, “D” and “E” reinforced concrete works are completed, the wall of top floors is laid by concrete wall blocks.

In 4-th building reinforced concrete works is completed, the wall of top floors is laid by concrete wall blocks.

We will remind that construction works in "Renessans Palace" began in May of the 2014th year.

Construction works in an 18-storeyed housing estate of a premium class will be completed in the first half of the 2017th year.